Meta Platforms

META in the public record.

No project record names META yet; its filings say what it has committed.

$355.73B
of leases signed but not yet started, commencing during the remainder of 2026 through 2036
In addition to the lease liabilities that are included on our balance sheet, we have operating and finance leases that have not yet commenced as of September 30, 2026. These lease obligations were approximately $355.73 billion, consisting of data centers, energy-related infrastructure, colocations, and certain network infrastructure, which will commence during the remainder of 2026 through 2036 with lease terms ranging from greater than one year to 30 years.
10-Q filed 2026-10-22

In its filings

LineLatest
Cash paid for property and equipment2026-01-01 to 2026-09-30 · 10-Q 2026-10-22$83.06B$48.31B a year before
Customer deposits / contract liabilitiesas of 2024-12-31 · 10-K 2025-01-30$721M$626M a year before
Purchase obligationsas of 2026-09-30 · 10-Q 2026-10-22$355.73B$58.14B a year before

SEC EDGAR: XBRL company facts and the filing's own text, parsed without a model. Each line links to its filing.

Contracts and suppliers

When records reach the P&L

RecordLine itemLag
Tax-incentive certificationEquipment capex0-12 months estimate
Ready-for-serviceRent; tenant lease liability; MSFT finance-lease capex0-3 months
Energization or customer acceptanceNeocloud revenue; depreciation startsat acceptance