IREN

IREN in the public record.

No project record names IREN yet; its filings say what it has committed.

In its filings

LineLatest
Cash paid for property and equipment2026-07-01 to 2026-09-30 · 10-Q 2026-11-05$2.13B$180M a year before
Remaining performance obligations (backlog)as of 2026-09-30 · 10-Q 2026-11-05$6.35B$195M a year before
Customer deposits / contract liabilitiesas of 2026-09-30 · 10-Q 2026-11-05$127M$1.1M a year before
Purchase obligationsas of 2025-09-30 · 10-Q 2025-11-06$198M

SEC EDGAR: XBRL company facts and the filing's own text, parsed without a model. Each line links to its filing.

Contracts and suppliers

When records reach the P&L

RecordLine itemLag
Tax-incentive certificationEquipment capex0-12 months estimate
Ready-for-serviceRent; tenant lease liability; MSFT finance-lease capex0-3 months
Energization or customer acceptanceNeocloud revenue; depreciation startsat acceptance