Anthropic, PBC
ANT in the public record.
3 data-center projects name a party that resolves to ANT.
Exposure estimate
3projects as owner, tenant, operator or permittee
0still need a discretionary vote
0.21projects expected to be blocked
–IT MW: not in record
Shared scenarios
- ERCOT pause on energising 75 MW+ data centers until Batch Zero results (2027-04-09)3 projects · 100% odds · 5-month delay if it happens
ERCOT's 75 MW line also counts projects whose size is not in record.
Each project counts once, shared by the parents named in the same role. Scenarios are listed, never added.